Name | Type | Posted | Actions |
|---|---|---|---|
Final Q and A Runway Intersection_20260603.xlsx | XLSX | Jun 11, 2026 | |
Solicitation Amendment FA441826R00120005 SF 30.pdf | Jun 11, 2026 | ||
Solicitation Amendment FA441826R00120004 SF 30.pdf | Jun 2, 2026 | ||
Solicitation Amendment FA441826R00120003 SF 30.pdf | May 20, 2026 | ||
Site Visit sign in sheet.pdf | May 14, 2026 | ||
Solicitation Amendment FA441826R00120002 SF 30.pdf | May 14, 2026 | ||
02 - SPEC PKG.2026 0414.FINAL.pdf | May 11, 2026 | ||
JB Charleston - Question and Answer Form.xlsx | XLSX | May 11, 2026 | |
Solicitation Amendment FA441826R00120001 SF 30.pdf | May 11, 2026 | ||
02-Specificatons .FINAL.pdf | May 7, 2026 | ||
05- Wage Determination Highway SC20260034 Charleston SC.pdf | May 7, 2026 | ||
04- Recovered Material Certification.pdf | May 7, 2026 | ||
03 - DKFX 1072314 - Total Performance Time.pdf | May 7, 2026 | ||
01-Drawings JBC Final.pdf | May 7, 2026 | ||
Solicitation - FA441826R0012.pdf | May 7, 2026 | ||
06 - Submittal Register.pdf | May 7, 2026 |
Repair Intersection Runway 03-21 & 15-33
Contact and place of performance
Brian T. Hawk
Charleston AFB, SC 29404
USA
Amendment 0005: The purpose of this amendment is to post the answers to the questions for this solicitation. Update concerning editable PDFs: PDFs in Solicitation appear to be password protected. In order to edit these documents you will need to save as (Microsoft Print to PDF or Convert to Microsoft Word, make edits and then save as Adobe PDF. Amendment 0004: The purpose of this Amendment is to extend th...
View moreIncludes performance of construction contract administration (Critical Path Method Scheduling, submittal management and closeout), multi-discipline efforts involving work on a secure Runway. Additionally, relevant performance includes performance of multi-discipline efforts involving removal and replacement of 136 individual pavement panels that measure 25 ft wide x 25 ft long x 24 inches deep, located at the intersection of the primary and secondary runway. Ability to perform work between hours of 2300-0700 hours Thursday through Monday. The work involves 3 primary activities each night including saw cutting, removal and installation of temporary panels, and placement of permanent panels. Show ability to construct permanent panels from fast setting concrete, capable of achieving the strength to handle aircraft traffic during a 3 -4-hour cure period. The runway intersection shall be open for daily aircraft traffic each morning. The project necessitates specialized capabilities and equipment, such as sawing and removal equipment for 24-inch pavement and volumetric mixers, sufficient in quantity to place a minimum of 50 cubic yards of fast setting concrete. Ancillary work includes milling and overlay of existing asphalt shoulders, installation of new runway centerline and edge lightings within the limits of work, installation of runway markings, pavement grinding for smoothness and pavement grooving, and incidental work that is similar or greater in scope, magnitude, and complexity than the effort described in this solicitation (Runway Asphalt and Concrete Repair and The evaluation of past performance information will take into Paving). Last, show ability to provide a work force capable of gaining clearance onto a secure flightline
The Department of the Air Force, through the 628th Contracting Squadron at Joint Base Charleston, has issued solicitation FA441826R0012 for the repair of the runway intersection for 03-21 and 15-33 at Charleston AFB, South Carolina. This construction project is categorized under NAICS 237310, Highway, Street, and Bridge Construction, and PSC Y1BD, Construction of Airport Runways and Taxiways. There is no set-aside designated for this requirement. Responses are due by June 18, 2026.
The scope of work involves multi-discipline construction efforts on a secure runway, specifically the removal and replacement of 136 individual pavement panels measuring 25 feet wide by 25 feet long and 24 inches deep. Contractors must be capable of performing work during a night shift from 23:00 to 07:00, Thursday through Monday, to ensure the runway intersection is open for daily aircraft traffic each morning. Primary activities include saw cutting, the installation of temporary panels, and the placement of permanent panels using fast-setting concrete capable of supporting aircraft traffic within a three-to-four-hour cure period. Specialized equipment requirements include sawing and removal tools for 24-inch pavement and volumetric mixers capable of placing at least 50 cubic yards of concrete per shift.
Ancillary tasks include milling and overlaying asphalt shoulders, installing new runway centerline and edge lighting, applying runway markings, and conducting pavement grinding and grooving. The project also encompasses construction contract administration services such as Critical Path Method scheduling, submittal management, and closeout. Administrative updates for this solicitation, including sixteen total attachments such as site visit records and question-and-answer forms, have been processed through five amendments. Brian T. Hawk serves as the primary point of contact for this requirement.
Generated by Lumen AI
Scoped analysis and attachments—go beyond the summary when you need detail from the solicitation package.