The Architect of the Capitol (AOC) has a requirement for a contract for Capitol Power Plant, with a period of performance of 180 Calendar Days. 1.1 CONGRESSIONAL Cable TV systems assessment BACKGROUND During the late 70’s, the first proposed 13 channel system was requested by both Senate Rules and House Administration. Starting with a single rack in the attic of the Russell Senate Office building, t...
View moreThe scope of this requirement is to engage the services of a professional vendor to submit a detailed assessment of the existing Architect of the Capitol Congressional Cable TV system (CCCTS) located at the “head end” Russell Senate office building, and the Capitol Power Plant Annex building. The vendor shall also provide a proposed improvement plan to the existing CCTS to improve content delivery. The assessment shall include detailed drawings of existing equipment specifications, connectivity layout, data flow and type. A final report detailing the findings shall be submitted delineating the existing system with the proposed improvements to the system, including cost, impact and duration. The objective of the assessment is to ensure the CCTS will meet the stringent demands of Congressional members and staff for a “24/7” operational environment.
The contractor shall perform the required task in accordance with the requirements of this contract.
• Technology Standards.
• Drawings; As Built Systems Drawings for CCTS
• Security specifications.
The contractor shall not deviate from any of the above documents without express approval granted by the Contracting Officer’s Representative (COR).
The contractor shall provide an existing CCTS system(s) assessment. Documenting, existing equipment specifications, connectivity layout, data flow and type. The assessment shall be completed in the CCTS primary head end located at Russell Senate Office building, and the secondary “Head End” at the Capitol Power Plant (CPP) Annex building. The results shall include a detailed, comprehensive report on the following below, but not limited to.
The contractor shall provide a comprehensive CCTS “improvement plan” to include a detailed report on proposed equipment upgrades or replacement, configuration, delivery, estimated cost, and impacts to existing system. The report shall provide options to the following items but not limited to the improvement plan.
Improvements to CCTS delivery via clear QAM 256 to outlying buildings and facilities (does not include assessment of outlying buildings and facilities but only the method of delivery).
The vendor shall provide a comprehensive CCTS control room “upgrade plan” at the Russell Senate Office Building to include a detailed report on equipment upgrades or replacement, configuration, delivery, estimated cost, and impacts to existing system. The report shall provide options for the following items but not limited to the improvement plan.
The contractor shall submit a Project Management Plan 30 days after award that outlines the project execution and project control approach, roles, responsibilities, cost, schedule, and scope. The plan shall be used to facilitate key decision points, milestones, and communication among key stake holders.
The contractor will prepare and deliver Biweekly Status Reports to the COTR and other specified individuals via electronic mail no later than 5:00 PM every other Friday. The intended audience includes: CCP Electronics Technician, CCP Electronics Engineer, CCP Senior management and Executive leadership from the Government and from the contractor.
Status reports will include the following information:
• Goals for the reporting period
• Accomplishments for the reporting period
• Recommendations for work to be accomplished during the next reporting period
• Risks to the successful and timely completion of the project
• Open Issues - Issues and risks summary
In accordance with TASK 1, 2 and 3. Reports shall be submitted in both native file (word) and Adobe acrobat (.pdf), in addition 10 printed and bounded reports.
Table 1 - Deliverables and Delivery Schedule
Deliverable/Description
Type
Delivery Method(s)
Delivery Date/Frequency
Kick-Off Meeting
Briefing
Virtual Meeting (Teams)
7 days after contract award
Project Management Plan
Document
MS Word / Adobe
14 days after contract award
Biweekly Status Report
Briefing
Virtual meeting and email document
Biweekly TBD
Tasks 1, 2, and 3 submittals (Draft)
Document
MS Word
6 months after contract award.
Tasks 1, 2, and 3 review
Briefing
Virtual meeting and email document
14 days after initial request
Final Task 1, 2 and 3 submittals
Document
MS Word
7 days prior to end of contract Period of Performance (PoP)
The contractor shall provide all deliverables via electronic methods, unless directed by the COR to provide hard copies, for review, approval, and appropriate action. Electronic copies shall be delivered via email attachment to the CO and COR as appropriate. The electronic copies shall be compatible with Microsoft Office 2010 or other applications as appropriate and mutually agreed to by the parties. Once created, deliverables and work products are considered the property of the Federal Government.
The deliverable shall be considered final upon receiving Government approval. The Government shall provide written notification of acceptance or rejection of all deliverables within two days of receipt. All notifications of rejection will be accompanied by an explanation of the specific deficiencies causing the rejection. Deliverables must be approved by the CO and COR to be considered “accepted.”
Deliverables shall be deemed acceptable if the document adequately covers all required topics, meets general quality measures, and is professionally prepared in terms of accuracy, clarity, format, and timeliness. Quality measures, as set forth below, shall be applied to each product received from the contractor.
No GFE provided
The contract type for this requirement is anticipated to be a Firm-Fixed Price (FFP). This is a firm-fixed-price contract that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. The contractor is full responsibility for all costs and resulting profit or loss.
The Period of Performance shall be 180 calendar days from Notice to Proceed.
Work under this requirement shall be performed at a government facility unless otherwise stated or approved. All equipment and office supplies will be provided at the government facility. Daily work hours shall be approved by the COR; however, core working hours for the contractor shall be 6:00 AM to 2:30 PM ET with a thirty-minute lunch break. Please be advised certain activities may require the vendor to work evening, or weekends to ensure no disruption occurs to Congressional activity and operations. Any contractor under this contract shall be required to perform work during these hours unless otherwise authorized. Overtime or compensation time shall not be performed unless specifically authorized by the contracting officer.
Travel is not authorized
This is not a personal services contract.
If under the performance of this contract the contractor requires access to AOC facilities, then the contractor will be escorted at all times. All contractor employees shall submit an E-Verify form and a United States Capitol Police background check form (CP-491) prior to the performance of work. Contractor employees shall also complete a contractor badging request form. All contractors working on site shall be required to wear an identification badge at all times. The AOC does not follow certain exceptions as described in the E-Verify federal contractor rule. Contractors are required to use E-Verify to verify that all employees working on AOC contracts are authorized to work in the United States. On site work may be interrupted because of Congressional events or U. S. Capitol Police requirements. All work to be performed is subject to government interruptions.
The AOC does not follow certain exceptions as described in the E-Verify federal contractor rule. Contractors are required to use E-Verify to verify that all employees working on AOC contracts are authorized to work in the United States.
The contractor shall follow all applicable safety guidelines. This project requires use of hard-hats and eye protection in designated areas. Contractors are required to wear “appropriate” clothing, i.e. Shorts and tee shirts will not be permitted. The Contractor shall be responsible for their own safety, and every precautionary measure shall be taken to protect themselves while at the US Capitol Power Plant, Satellite Antenna Array. Full PPE.
The contractor shall comply with all AOC safety policies and shall require all employees to wear appropriate clothing apparel for the assigned tasks. No sandals or any style of open toe shoes shall be allowed for any position that requires lifting of 5lbs or greater as this would pose a risk of injury.
Instructions for Responding to this RFI:
Please provide a response to the following questions from the Government:
a) Will your company be interested in submitting a quotation for this contract if a solicitation is issued?
b) Can your company perform this scope of work under its GSA Schedule contract? If so, what is the GSA Schedule contract number? What SIN is this usually done under? Or is this a mix of SINs?
c) What questions do you have for the Government? (You may either list your questions in the RFI response or you may email the questions to Donald Fuqua at [email protected] any time if it helps you to provide a better response with the answers known)
d) What is the usual duration of a contract for this work? In other words, what period of performance is typical for this?
e) Please provide examples of past contracts within the past three years that are either completed or ongoing that have the same or similar scope of work. Please provide the awarded contract dollar amount as well.
f) Any other information you believe will be of interest to the Government.
Please email responses to Donald Fuqua at [email protected] by noon on April 24, 2026.
Thank you,
Donald Fuqua
Contracting Officer
Mobile: (202) 329.6763
Architect of the Capitol
Supplies, Services, and Material Management Division (SSMMD)
www.aoc.gov
The Architect of the Capitol (AOC) has issued this Sources Sought notice to identify professional vendors capable of assessing the Congressional Cable TV System (CCCTS). The project requires a detailed technical evaluation of the existing head-end infrastructure located at the Russell Senate Office Building and the Capitol Power Plant Annex. The selected contractor will be responsible for documenting current equipment specifications, connectivity layouts, and data flow, while also developing a comprehensive improvement plan to enhance content delivery, system resiliency, and security for 24/7 operations. Key tasks include producing an upgrade plan for the control room and exploring advanced delivery methods such as IP streaming, mobile application integration, and Free Ad-Supported Streaming TV (FAST) channel ingestion.
This requirement is classified under NAICS 517111, Wired Telecommunications Carriers, and PSC DG11, IT and Telecom - Network: Satellite Communications and Telecom Access Services. There is currently no set-aside acronym/code or explanation assigned to this procurement. The anticipated contract type is Firm-Fixed Price with a performance period of 180 calendar days from the Notice to Proceed. Work will be performed on-site in Washington, DC, primarily during core hours of 6:00 AM to 2:30 PM ET, though evening or weekend work may be necessary to avoid disrupting Congressional operations. All contractor personnel must undergo E-Verify and United States Capitol Police background checks.
Responses to this notice are due by April 24, 2026, and should be submitted via email to the primary point of contact, Donald Fuqua. Submissions must address the vendor's ability to perform the scope of work, relevant GSA Schedule information, and examples of similar past performance within the last three years. The information gathered from this market research will assist the AOC in finalizing its acquisition strategy for the assessment and modernization of the cable systems serving the House and Senate.
Generated by Lumen AI
Scoped analysis and attachments—go beyond the summary when you need detail from the solicitation package.