Award ID | Description | Recipient | Total Value | Awarding Agency | Funding Agency | Set Aside | NAICS | PSC | Award Date | Start Date | End Date | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| MONITORING SPRINGS AND SEEPS AT BLUFF B. | TETRA TECH, INC. | $31,472 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jun 28, 2023 | Jan 16, 2018 | Dec 31, 2024 | ||
| CONSTRUCTION OVERSIGHT FOR RILEY PASS | TETRA TECH, INC. | $104,382 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jun 28, 2023 | Jan 16, 2018 | Dec 31, 2024 | ||
| RILEY PASS 2024 SEDIMENT MONITORING BLUFF B_TO36 | TETRA TECH, INC. | $12,091 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jun 28, 2023 | Jan 16, 2018 | Dec 31, 2024 | ||
| RILEY PASS 2024 CONSTRUCTION AIR MONITORING _TO39 | TETRA TECH, INC. | $39,025 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jun 28, 2023 | Jan 16, 2018 | Mar 1, 2025 | ||
| RILEY PASS 2025 BLUFF B RECLAMATION ENGINEERING PLANS_TO 35. | TETRA TECH, INC. | $104,825 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jun 28, 2023 | Jan 16, 2018 | Dec 31, 2024 | ||
| RILEY PASS REVEGETATION AND SUBSIDENCE MONITORING 2024_TO38 | TETRA TECH, INC. | $76,139 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jun 28, 2023 | Jan 16, 2018 | Dec 31, 2024 | ||
| 2024 BLUFF B EXCAVATION ENGINEERING DESIGN | TETRA TECH, INC. | $100,823 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 30, 2023 | Mar 30, 2023 | Nov 30, 2023 | ||
| RILEY PASS FY23 BLUFF B SPRING/SEEP INVESTIGATION_TO33 | TETRA TECH, INC. | $39,432 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 13, 2023 | Mar 13, 2023 | Dec 31, 2023 | ||
| SUBSIDENCE MONITORING AT BLUFF A (YEAR-1) AND BLUFF I (YEAR-5) AT RILEY PASS TO EVALUATE THE STABILITY OF THE RECLAMATION. | TETRA TECH, INC. | $13,058 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Feb 1, 2023 | Feb 1, 2023 | May 1, 2024 | ||
| RILEY PASS BLUFF B SEDIMENT MONITORING PLAN_TO32 | TETRA TECH, INC. | $2,376 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Feb 1, 2023 | Feb 1, 2023 | May 30, 2024 | ||
| CONSTRUCTION INSPECTION OVERSIGHT FOR THE WORK OCCURRING IN 2023 ON BLUFF B AND INCLUDES VERIFICATION SAMPLING AFTER WORK HAS BEEN COMPLETED. | TETRA TECH, INC. | $333,261 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Feb 1, 2023 | Feb 1, 2023 | Feb 29, 2024 | ||
| GROSS ALPHA AIR MONITORING, ARSENIC AIR MONITORING, AND VIBRATION MONITORING DURING FY23 CONSTRUCTION WORK AT RILEY PASS. TO-28 | TETRA TECH, INC. | $58,495 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Jan 27, 2023 | Jan 27, 2023 | Mar 1, 2024 | ||
| MONITORING ON SITE TO EVALUATE STATUS OF VEGETATION GROWTH WITH RESPECT TO SOIL COVERAGE AS WELL AS VARIETY OF SPECIES INCLUDING INVASIVE SPECIES COMBINED WITH A SUMMARY REPORT. | TETRA TECH, INC. | $40,085 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Sep 30, 2022 | Sep 30, 2022 | Dec 30, 2023 | ||
| RILEY PASS FY22 BLUFF I - YEAR 4 MONITORING_TO26 | TETRA TECH, INC. | $3,184 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Sep 1, 2022 | Sep 1, 2022 | Mar 30, 2023 | ||
| RILEY PASS FY22 SITE PERSONNEL RADIATION MONITORING, AS PER STATEMENT OF WORK | TETRA TECH, INC. | $12,904 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Apr 14, 2022 | Apr 1, 2022 | Jan 15, 2023 | ||
| PRE-CONSTRUCTION PREPARATION AND DOCUMENT REVIEW, CONSTRUCTION OVERSIGHT/INSPECTION, VERIFICATION SAMPLING AND ANALYSIS, CONSTRUCTION COMPLETION REPORT, AND PROJECT MANAGEMENT FOR RILEY PASS BLUFF B | TETRA TECH, INC. | $157,313 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 10, 2022 | Mar 10, 2022 | Dec 30, 2022 | ||
| BLUFF B BASELINE SEDIMENT MODELING TO 24 | TETRA TECH, INC. | $18,059 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 10, 2022 | Mar 10, 2022 | Jul 1, 2022 | ||
| RILEY PASS BLUFF B SITE VISIT, CONCEPTUAL EXCAVATION AND NATURAL LANDFORM PLAN, CONTRACTING PACKAGE, AND PROJECT MANAGEMENT. | TETRA TECH, INC. | $159,766 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 10, 2022 | Mar 10, 2022 | Mar 31, 2023 | ||
| FY21_RILEY PASS_SUBSURFACE INVESTIGATION FOR EASTERN AREA OF BLUFF B_TO 19 | TETRA TECH, INC. | $189,664 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | May 20, 2021 | May 20, 2021 | Mar 31, 2023 | ||
| TASK ORDER 20 AT RILEY PASS FOR BLUFF J VERIFICATION SAMPLING. | TETRA TECH, INC. | $28,495 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Apr 15, 2021 | Apr 15, 2021 | Jan 15, 2022 | ||
| FY21 RILEY PASS SOIL BORROW SOURCE VERIFICATION | TETRA TECH, INC. | $46,070 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Apr 7, 2021 | Apr 7, 2021 | Jan 15, 2023 | ||
| FY21 SLOPE STABILITY AND REVEGETATION MONITORING TO NO. 17 | TETRA TECH, INC. | $47,414 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 12, 2021 | Mar 12, 2021 | Dec 30, 2022 | ||
| RILEY PASS VEGETATION MONITORING | TETRA TECH, INC. | $12,330 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Mar 12, 2021 | Mar 12, 2021 | Dec 30, 2022 | ||
| FY21 RILEY PASS TO16_NE QUADRANT BLUFF B ENGINEERING DESIGN PACKAGE | TETRA TECH, INC. | $153,425 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Dec 2, 2020 | Dec 2, 2020 | May 30, 2021 | ||
| RILEY PASS EXISTING CONDITIONS REPORT | TETRA TECH, INC. | $0 | FOREST SERVICE | FOREST SERVICE | — | 541330Engineering Services | C219ARCHITECT AND ENGINEERING- GENERAL: OTHER | Sep 1, 2020 | Sep 1, 2020 | Dec 31, 2020 |